Lakeview-Nuevo MDP Laterals D & E Project
Project Scope
This District-led project will eliminate the existing Federal Emergency Management Agency (FEMA) floodplain downstream of the existing Lakeview Dam by collecting flows from the dam’s low-level outlet pipe and conveying the flows in approximately 1.75 miles of underground storm drain westerly along Water Avenue to the existing Nuevo Channel at Yucca Avenue and 11th Street. The project will also reduce flooding to the community by including a detention basin south of Water Avenue to capture and detain runoff and will include Lateral E along Bell Avenue which will reduce flooding along the street and to the community west of Bell Avenue. The District will be responsible for operation and maintenance of the storm drain and basin improvements.
Contact
Ryan Gosliga, P.E.
P: 951-955-1205
E: [email protected]